The three substations of Moray East Offshore Windfarm were prepared onshore. V&SH Offshore performed the pulling, routing, termination and testing of 57 HV cables and 9 FO cables establishing the circuits for the offshore connections between the substations and the strings.
Onshore Preparation
By performing as much of this scope onshore, both costs and risk for our client could be minimized in comparison with execution offshore. In addition, V&SH was able to identify and solve multiple matters which could result in offshore implications due to our exceptional experience in offshore terminations
“Being able to assist our clients with our knowledge and experience, even if it outreaches our scope, is what we as V&SH Offshore are proud of.”